This project is funded by KICUKIRO District and the construction contract was entrusted to RGEC & C LTD for the amount 262,971,536 Frw with the supervision awarded to FIRST SOLUTION COMPANY for amount 3,360,000 Frw. The works consist of the construction of an administrative office of two floors and the plot layouts which started on 06/05/2014 for duration of 6 months.
The project experienced delays in the execution of works from September 2014 to January 2015 due to poor cash flow by the contractor. However, works have resumed and the progress to date is at 96%.