The ongoing phase (unconditional) of the project consists of rehabilitation of the main road crossing the Central Business District from KOBIL Petrol station to PENDEZA and “contournement du marché”.
During the tendering process for hiring the construction company and the supervising firm, ASSETIP provided technical support in revision of Bills of quantities, revision of the tender document for construction and in revision of the Request for Proposal for hiring the supervision firm.
Construction works started in August 2015 for a period of 4 months. By the end of March 2016, the overall physical progress of works was at 94%.
A saving of 210.000.000 FRW has been obtained after revision of the Bills of quantities. A portion of this amount has been relocated for complementary works (outlets). In addition to that a saving of 3,252,400FRW has been done during the contract negotiation for the supervision of works through the ASSETIP’s advice.
Road before contruction works (left) and after laying the asphalt layer (right)